Darley Service Road upgrade
Service Road Construction Darley, including flexible pavement construction and associated underground drainage, kerb and channel and footpath.
Project required the use of a static roller to ensure no damage was caused to existing services - especially to the AC water main located just below the flexible pavement layer. Civil works commenced in July 2021 and were completed in 4 weeks - on time and on budget.
​
SCOPE OF WORK
-
Earthworks
-
Pavement construction
-
Kerb and channel
-
Drainage
-
Prime and Asphalting
-
Site clean up
​